Office and hotel complex “Airport-City” near the state enterprise MA “Boryspil”
List of works
Design work of the office center of the first stage A1A2, stage “Project”:
Internal engineering networks:
- Power supply, electric lighting;
- Heating, ventilation and air conditioning;
- Water supply, sewerage and storm sewerage;
- Roof-top boiler room of open atmospheric design (peak);
- Climate station – air heat pump, chiller.
- Vertical transport;
- Gas supply;
- Communication systems;
- Automation and dispatching;
- Fire extinguishing and fire alarm;
- EIA;
External networks and facilities:
- Water well;
- Treatment facilities for rain and melt water;
- VK external networks;
- External power supply networks 10kV;
- Transformer substation 2BKTP 1000kVA;
- Diesel power plant DG 100kVA;
- Gas holder 10m3